      Source (1)

      Later this month the LA Board of Water and Power Commissioners is expected to approve a 25-year contract that will serve 7 percent of the city’s electricity demand at 1.997¢/kwh for solar energy and 1.3¢ for power from batteries.

      The project is 1 GW of solar, 500MW of storage. They don’t specify storage capacity (MWh). The source provides two contradicting statements towards their ability to provide stable supply: (a)

      “The solar is inherently variable, and the battery is able to take a portion of that solar from that facility, the portion that’s variable, which is usually the top tend of it, take all of that, strip that off and then store it into the battery, so the facility can provide a constant output to the grid”

      And (b)

      The Eland Project will not rid Los Angeles of natural gas, however. The city will still depend on gas and hydro to supply its overnight power.

      Source (2) researches “Levelized cost of energy”, a term they define as

      Comparative LCOE analysis for various generation technologies on a $/MWh basis, including sensitivities for U.S. federal tax subsidies, fuel prices, carbon pricing and cost of capital

      It looks at the cost of power generation. Nowhere does it state the cost of reaching 90% uptime with renewables + battery. Or 99% uptime with renewables + battery. The document doesn’t mention uptime, at all. Only generation, independant of demand.

      To the best of my understanding, these sources don’t support the claim that renewables + battery storage are costeffective technologies for a balanced electric grid.

      • Blue_Morpho@lemmy.world
        link
        fedilink
        English
        arrow-up
        1
        ·
        1 hour ago

        It looks at the cost of power generation

        Yes.

        But then you added the requirement of 90% uptime which is isn’t how a grid works. For example a coal generator only has 85% uptime yet your power isn’t out 4 hours a day every day.

        Nuclear reactors are out of service every 18-24 months for refueling. Yet you don’t lose power for days because the plant has typically two reactors and the grid is designed for those outages.

        So the only issue is cost per megawatt. You need 2 reactors for nuclear to be reliable. That’s part of the cost. You need extra bess to be reliable. That’s part of the cost.